30. Which answer lists the proper steps required to develop a disaster recovery and business continuity plan (DRP/BCP)?


Вариант ответа 1 - A. Project initiation, business impact analysis, strategy development, plan development, testing, maintenance.

Вариант ответа 2 - B. Strategy development, project initiation, business impact analysis, plan development, testing, maintenance.

Вариант ответа 3 - C. Business impact analysis, project initiation, strategy development, plan development, testing, maintenance.

Вариант ответа 4 - D. Project initiation, plan development, business impact analysis, strategy development, testing, maintenance.